back

Itobe Power Plant

folder

Itobe Power Plant

14

eyemarked

3

REVIEWS

negative

AVG. SENTIMENT

It is located in Kogi State. Its capacity is 600MW and its type is CFB Tech Coal. Future Expansion: 1200MW. Project cost is estimated at US$1.2 billio...

SUPERVISING MDA

Itobe Power Plant

FEDERAL MINISTRY OF POWER

KOGI

STATES

10011111

project CODE

ELECTRICITY, GAS, STEAM AND AIR CONDITIONING SUPPLY

SECTOR

-

DEPARTMENT

Ongoing

PROJECT STATUS

30%

completed

Eyemark

$5.00B

TOTAL PROJECT COST

Eyemark

7 Years

PROJECT TIMELINE

Eyemark

1st Jan 2015

START DATE

Eyemark

31st Dec 2022

END DATE

appropriated

_

TOTAL APPROPRIATED

spent

_

AMOUNT SPENT SO FAR

children

None

CHILDREN PROJECT

page-views

18469

PAGE VIEWS

Project Description

Below explains what this project is all about.

It is located in Kogi State. Its capacity is 600MW and its type is CFB Tech Coal. Future Expansion: 1200MW. Project cost is estimated at US$1.2 billion.

Contractors

Below are the contractors working on this project.

contractor-avatar

Eta-Zuma Group

Sustainable Development Goals (0)

Below are the Sustainable Development Goals this project targets.

Project Location 1

Project Reviews

view all

general sentiment

sentiment

negative

3 Reviews

positive

sentiment

1

neutral

sentiment

1

negative

sentiment

1

Project Updates (0)

see all