Construction Of Futo Central Store
-
eyemarked
-
REVIEWS
-
AVG. SENTIMENT
Construction Of Futo Central Store...
SUPERVISING MDA
FEDERAL MINISTRY OF EDUCATION
IMO
STATES
•
ERGP23156106
project CODE
•
CONSTRUCTION, Education
SECTOR
•
-
DEPARTMENT
Ongoing
PROJECT STATUS
80%
completed
₦84.73M
TOTAL PROJECT COST
5 Months
PROJECT TIMELINE
8th Mar 2021
START DATE
23rd Aug 2021
END DATE
₦77.00M
TOTAL APPROPRIATED
₦69.90M
AMOUNT SPENT SO FAR
None
CHILDREN PROJECT
119
PAGE VIEWS
Below explains what this project is all about.
Contractors
Below are the contractors working on this project.
Sustainable Development Goals (1)
Below are the Sustainable Development Goals this project targets.
INDUSTRY, INNOVATION AND INFRASTRUCTURE
Project Location 1
Project Reviews
general sentiment
No reviews yet
positive
0
neutral
0
negative
0
Project Updates (1)
Project Update On Construction Of Futo Central Store
These are some of the results of the monitoring and evaluation exercise done on Construction Of Futo Central Store as at 23rd August, 2022