Construction And Furnishing Of Post Natal Wing Of Maternity Ward
-
eyemarked
-
REVIEWS
-
AVG. SENTIMENT
Construction And Furnishing Of Neo-Natal Wing Of Maternal And Chilcare Complex...
SUPERVISING MDA
FEDERAL MINISTRY OF HEALTH
TARABA
STATES
•
ERGP25114143
project CODE
•
HUMAN HEALTH AND SOCIAL SERVICES, CONSTRUCTION
SECTOR
•
-
DEPARTMENT
Ongoing
PROJECT STATUS
95%
completed
₦214.82M
TOTAL PROJECT COST
-
PROJECT TIMELINE
-
START DATE
-
END DATE
₦213.60M
TOTAL APPROPRIATED
₦136.72M
AMOUNT SPENT SO FAR
None
CHILDREN PROJECT
250
PAGE VIEWS
Below explains what this project is all about.
Contractors
Below are the contractors working on this project.
Sustainable Development Goals (1)
Below are the Sustainable Development Goals this project targets.
INDUSTRY, INNOVATION AND INFRASTRUCTURE
Project Location 1
Project Reviews
general sentiment
No reviews yet
positive
0
neutral
0
negative
0
Project Updates (0)